How Long Does It Take to Install New Kitchen Cabinets?
The time to install kitchen cabinets depends on the kitchen size, cabinet type, and whether you're hiring professionals or DIY-ing. Here's a detailed breakdown:
1. Average Timelines
| Project Scope | DIY Time | Professional Time |
|---|---|---|
| Small Kitchen (10x10 ft) | 2–5 days | 1–3 days |
| Medium Kitchen (12x15 ft) | 5–7 days | 3–5 days |
| Large/Custom Kitchen | 7–14+ days | 5–10 days |
2. Factors Affecting Installation Time
Cabinet Type:
Stock/RTA Cabinets: Faster (pre-assembled or easy-to-assemble).
Custom Cabinets: Longer due to precise fitting and adjustments.
Prep Work:
Removing old cabinets: Adds ½–1 day.
Wall/floor repairs: Adds 1–2 days.
Complexity:
Islands, angled walls, or soffits: +1–3 days.
Plumbing/electrical adjustments: +1–2 days.
3. Step-by-Step Breakdown
Professional Installation
Day 1: Remove old cabinets, prep walls/floors.
Day 2: Install base cabinets and secure to studs.
Day 3: Install wall cabinets, align doors/drawers.
Day 4: Add trim, crown molding, and hardware.
DIY Installation
Day 1–2: Assemble RTA cabinets and prep walls.
Day 3–4: Install base cabinets.
Day 5–6: Install wall cabinets.
Day 7: Adjust doors, add hardware, and finish trim.
4. Tips to Speed Up Installation
Pre-Assemble Cabinets: Complete RTA units before installation day.
Use a Laser Level: Ensure alignment accuracy and reduce adjustments.
Rent Tools: A cabinet jack ($30/day) simplifies lifting uppers.
5. Common Delays
Missing Parts: Common with RTA cabinets (+1–2 days).
Uneven Walls: Requires shimming (+4–8 hours).
Appliance Conflicts: Adjusting for dishwasher/oven cutouts (+½ day).
6. When to Hire a Pro
Tight deadlines or complex layouts.
Lack of tools/experience (prevents costly mistakes).
High-end cabinets requiring expert handling (e.g., lacquered finishes).
\boxed{
Final Answer:
DIY: 2–7 days for a standard kitchen (10x10 ft).
Professional: 1–5 days for the same space.
Add 1–3 days for custom cabinets or complex layouts.
Pro Tip: Schedule cabinet installation after flooring (if using permanent materials like tile/hardwood) to avoid alignment issues. For floating floors, install cabinets first! 🔧